• The site will be open on Martin Luther King Day, January 15th with permit approvals from DDOT & DOB.
• Work will typically take place from 7:00AM to 7:00PM. On a case by-case-basis, permitted work may continue beyond 7:00PM but will mainly entail clean-up and site preparation for the following work day.
• 4th St NE will remain closed to non-construction related traffic and parking. Parking in front of the construction gates on 4th St NE is prohibited.
• There will no longer be non-construction parking allowed along the north side of Ingraham between South Dakota and where Ingraham turns into Hamilton. This permitted closure will be used for construction activity only.
• There will be miscellaneous deliveries throughout the week. Traffic control personnel will be present to assist for safe pedestrian passage.
• A temporary sidewalk is in place along S. Dakota Avenue. Please take note of pedestrian and traffic control signs at the Ingraham & Kennedy St. intersections.
• See below for Rocketship Public School and the Social Justice School Information and traffic patterns for next week.
• The Rocketship Public School & The Social Justice School will have a short school week (Tuesday – Friday 8:25 am - 3:45 pm). Please follow the typical traffic patterns shown below.
Contact Info: Please send any questions or concerns to [email protected] or call 202-517-1919.
Art Place FEZ LLC