Construction Updates

Construction Update Notice 01.01.2024 - 01.06.2024
Monday, January 1, 2024
through
Saturday, January 6, 2024

• The Jobsite will be closed on New Year’s Day – Monday, January 1st.
• The remainder of the week, work will typically take place from 7:00AM to 7:00PM. On a case by-case-basis, permitted work may continue beyond 7:00PM but will mainly entail clean-up and site preparation for the following work day.
• 4th St NE will remain closed to non-construction related traffic and parking. Parking in front of the construction gates on 4th St NE is prohibited.
• As the project progresses construction traffic is expected to continue, utilizing Ingraham and Kennedy St. to enter and exit the site.
• There will no longer be non-construction parking allowed along the north side of Ingraham between South Dakota and where Ingraham turns into Hamilton. This permitted closure will be used for construction activity only.
• There will be miscellaneous deliveries throughout the week. Traffic control personnel will be present to assist for safe pedestrian passage.
• A temporary sidewalk is in place along S. Dakota Avenue. Please take note of pedestrian and traffic control signs at the Ingraham & Kennedy St. intersections.
• See below for Rocketship Public School and The Social Justice School information and traffic patterns for next week.

• Rocketship Public School and The Social Justice School will be on Holiday break through January 2nd. For all the remainder of the week will follow the typical traffic patterns shown below.
• The Rocketship Public School & The Social Justice School will have a short week (Wednesda – Friday 8:25 am - 3:45 pm).

Contact Info: Please send any questions or concerns to hello@fezartplace.com or call 202-517-1919.

Art Place FEZ LLC

This notice will be updated and circulated weekly.