Construction Update Notice 04.22.2024 - 04.27.2024
Monday, April 22, 2024
through
Saturday, April 27, 2024

• Work will typically take place from 7:00AM to 7:00PM. On a case by-case-basis, permitted work may continue beyond 7:00PM but will mainly entail clean-up and site preparation for the following work day.
• 4th St NE will remain closed to non-construction related traffic and parking. Parking in front of the construction gates on 4th St NE is prohibited.
• There will no longer be non-construction parking allowed along the north side of Ingraham St NE, between South Dakota Ave NE and Hamilton St NE. This permitted closure will be used for construction activity only.
• There will be miscellaneous deliveries throughout the week. Traffic control personnel will be present to assist for safe pedestrian passage.
• The building’s fire alarm system will undergo testing and will be monitored by the construction team. Please note the fire alarm alert system will be sounding off throughout the week and is not a health & safety concern during work hours.
• A temporary sidewalk is in place along South Dakota Avenue. Please take note of pedestrian and traffic control signs at the Ingraham St NE and Kennedy St NE intersections.
• See below for Rocketship Public School and the Social Justice School Information and traffic patterns for next week.

• The Rocketship Public School & The Social Justice School will have a full school week Monday – Friday. Please follow the typical traffic patterns shown below for traffic as needed.

Contact Info: Please send any questions or concerns to [email protected] or call 202-517-1919.

Art Place FEZ LLC

This notice will be updated and circulated weekly.