Construction Update Notice 05.16.2022 - 05.21.2022
Monday, May 16, 2022
through
Saturday, May 21, 2022

• Work will typically take place from 7:00AM to 4:00PM but special permits currently allow us to work until 7:00pm if necessary.
• 4th St NE will remain closed to non-construction related traffic and parking. Parking in front of the construction gates on 4th St NE is prohibited.
• 3rd Street roadwork work will continue. Residential parking access from 3rd St. will be closed during work hours.
• Site excavation will continue into the summer months. Construction traffic is expected to increase, utilizing Ingraham and Kennedy St. to enter and exit the site.
• Roadwork on South Dakota Ave will continue, with temporary lane closures from 9:30am-3:30pm.

Contact Info: Please send any questions or concerns to hello@fezartplace.com or call 202-517-1919.

Art Place FEZ LLC

This notice will be updated and circulated weekly.