Construction Update Notice 07.27.2020 - 08.10.2020
Monday, July 27, 2020
through
Monday, August 10, 2020
Work will take place from 7:00AM to 4:00PM unless special permit allow otherwise.
4th St NE will remain closed to non-construction related traffic and parking.
Barricade fencing will be shifted along the west of S. Dakota Ave sidewalk as the New Pepco Duct Bank work continues.
Dry utility trench work for Pepco is on-going along the west side of S. Dakota Ave sidewalk and across Kennedy St NE & Dakota Ave NE intersection. Vehicular and pedestrian traffic will be maintained per DDOT requirements. Barricade fencing will separate the workers and equipment from the S. Dakota Ave sidewalk.
DDOT approved traffic control measures for pedestrians and vehicles will be used for the utility work & restoration work. Travel lanes in both directions on Kennedy St NE near the intersection of S. Dakota Ave will be made narrower during the test hole work. Certified flaggers will be on location to direct traffic when required.
Sidewalk restoration work along S. Dakota Ave is anticipated to begin week August 6 (+/-).
Equipment for the raze / demolition of the (7) vacant buildings along the 4th St NE anticipated to be mobilized to the site and starting July 28 (+/-).
Callahan Alley will remain closed to non-construction vehicles equipment.
Water line installation work is on-going in the roadway of 3rd St NE for water line work. During construction of these improvements, the bike path and sidewalk connecting 3rd St NE will remain accessible.