Construction Update Notice 08.15.2022 - 08.20.2022
Monday, August 15, 2022
through
Saturday, August 20, 2022

• Work will typically take place from 7:00AM to 4:00PM but special permits currently allow us to work until 7:OOPM if necessary.
• 4th St NE will remain closed to non-construction related traffic and parking. Parking in front of the construction gates on 4th St NE is prohibited.
• 3rd St. Road extension will remain closed to vehicle traffic, sidewalks will be open for pedestrian access.
• Site excavation will continue into the summer months. Construction traffic is expected to continue, utilizing Ingraham and Kennedy St. to enter and exit the site.
• Please note construction equipment will be staged on Kennedy St. for utility work during work hours. Traffic control personnel will be present to assist for safe passage of pedestrian vehicles.
• See page 2 for Rocketship Public School and The Social Justice School information and traffic patterns for next week.

Contact Info: Please send any questions or concerns to hello@fezartplace.com or call 202-517-1919.

Art Place FEZ LLC

This notice will be updated and circulated weekly.