Construction Update Notice 08.22.2022 - 08.27.2022
Monday, August 22, 2022
through
Saturday, August 27, 2022

• Work will typically take place from 7:00AM to 4:00PM but special permits currently allow us to work until 7:OOPM if necessary.
• 4th St NE will remain closed to non-construction related traffic and parking. Parking in front of the construction gates on 4th St NE is prohibited.
• 3rd St. Road extension will remain closed to vehicle traffic, sidewalks will be open for pedestrian access.
• Site excavation will continue into the summer months. Construction traffic is expected to continue, utilizing Ingraham and Kennedy St. to enter and exit the site.
• Please note construction equipment will be staged on Kennedy St. and Ingraham St. for utility work during work hours. Traffic control personnel will be present to assist for safe passage of pedestrian vehicles.
• See page 2 for Rocketship Public School and The Social Justice School information and traffic patterns for next week.

Contact Info: Please send any questions or concerns to hello@fezartplace.com or call 202-517-1919.

Art Place FEZ LLC

This notice will be updated and circulated weekly.