Construction Update Notice 09.21.2020 - 10.05.2020
Monday, September 21, 2020
through
Monday, October 5, 2020
  • Work will take place from 7:00AM to 4:00PM unless special permit allow otherwise.
  • 4th St NE will remain closed to non-construction related traffic and parking. Sidewalks on 4th St NE will not be accessible from Kennedy St NE.
  • Barricade fencing will be shifted along the west of S. Dakota Ave sidewalk as the New Pepco Duct Bank work continues.
  • Dry utility trench work for Pepco may be completed week of September 21st along the west side of S. Dakota Ave NE north of Kennedy St NE.
  • DDOT approved traffic control measures for pedestrians and vehicles will be used for the utility work & restoration work. Certified flaggers will be on location to direct traffic when required.
  • Sidewalk restoration work along S. Dakota Ave is anticipated to begin week September 21 (+/-).
  • Raze / demolition of the (7) vacant buildings along 4th St NE is on-going.
  • Callahan Alley will remain closed to non-construction vehicles equipment.
  • Sidewalk restoration on Kennedy St NE located between 4th St NE and Callahan Alley.

Contact Info:

Please send any questions or concerns to hello@fezartplace.com or call 202-517-1919

Art Place FEZ LLC 

The Morris & Gwendolyn Cafrtiz Foundation

This notice will be updated and circulated weekly.