Construction Update Notice 11.20.2023 - 11.25.2023
Monday, November 20, 2023
through
Saturday, November 25, 2023

• Work will typically take place from 7:00AM to 7:00PM. On a case by-case-basis, permitted work may continue beyond 7:00PM but will mainly entail clean-up and site preparation for the following work day.
• 4th St NE will remain closed to non-construction related traffic and parking. Parking in front of the construction gates on 4th St NE is prohibited.
• The site will be closed this Thursday (11/23) for the Thanksgiving Holiday. Site operations will continue the remainder of the week.
• There will no longer be non-construction parking allowed along the north side of Ingraham between South Dakota and where Ingraham turns into Hamilton. This permitted closure will be used for construction activity only.
• There will be miscellaneous deliveries throughout the week. Traffic control personnel will be present to assist for safe pedestrian passage.
• Note: The tower crane removal process will begin this week. Please be advised of increased tractor trailer traffic around the site.
• Please be advised that we will have utility work taking place on South Dakota Ave with sidewalk and selective lane closures every weekday. There will be traffic control personnel present during working hours.
• Rocketship Public School & The Social Justice School will be on fall break this week (11/20-11/24). Typical drop-off & pick-up traffic patterns will continue next week.

Contact Info: Please send any questions or concerns to [email protected] or call 202-517-1919.

Art Place FEZ LLC

This notice will be updated and circulated weekly.