Construction Update Notice 02.07.2022 - 02.12.2022
Monday, February 7, 2022
through
Saturday, February 12, 2022


  • Work will take place from 7:00AM to 4:00PM unless special permits allow otherwise. 
  • 4th St NE will remain closed to non- construction related traffic and parking. Sidewalks on 4th St NE will not be accessible from Kennedy St NE. Parking in front of the construction gates on 4th St NE is prohibited. 
  • Callahan Alley will remain closed to non-construction vehicles and equipment. 
  • Excavation material layout to continue, with construction traffic expected on Kennedy and Ingraham St. 
  • We will continue installing the support of excavation (SOE) along South Dakota Ave, working towards Ingraham St. Please be advised this activity involves moderate noise disturbance during our work hours. 
  • Saturday, February 12th, we will be holding a ground-breaking ceremony for this project from 11am-12pm (by invitation only). The event will take place at the south end of 4th St, with set-up beginning at 7:30am. Please note traffic is to be expected on Ingraham around event hours.

Contact Info:

Please send any questions or concerns to [email protected] or call 202-517-1919

Art Place FEZ LLC 

The Morris & Gwendolyn Cafrtiz Foundation

This notice will be updated and circulated weekly.