September 22, 2025

Art Place Construction Update: September 22, 2025

Social Justice Construction Update at Kennedy & 3rd Street NE

Construction Activities

•Interior building demolition and removal of existing windows will continue the week of 9/22 and

will last for several weeks.

•Site demolition is anticipated to begin towards the middle/end of October.

•As the project progresses, this Construction Update will be used to notify the community of large

deliveries and upcoming construction activities that could impact surrounding neighbors.

If at any time there are questions or concerns regarding the Social Justice School construction site or project, please feel free to reach out to the following L.F. Jennings employees:

Andrew Mitchell – On-Site Superintendent

(571) 265-7884

Vincent Wilkinson – Project Manager

(571) 419-7917